cost : actual & budget

1 reply [Last post]
Amir Dadbakhsh
User offline. Last seen 3 years 19 weeks ago. Offline
Joined: 13 Oct 2004
Posts: 42
hi guys
I faced the problem and i need somebody to give me hand to solve my problem.
i work for oil company and our project contains about atleast 500 tasks.it,s really hard to write budget cost and cost at completion for each task especially we always face the change order that make change our cost at completion so Iam looking for a way to link enterprise and msp to transfer cost from msp to enterprise.
i would be really glad to have your advice on it.

Replies

masoud rahimian
User offline. Last seen 14 years 50 weeks ago. Offline
Joined: 16 Aug 2004
Posts: 13
Groups: None
Dear Dadbakhsh
why linking to MSP??you can link enterprise to MsSql Or oracle and Update any field automaticaly from your Company MIS or any Software.

Masoud