date

5 replies [Last post]
Forum Guest
User offline. Last seen 2 years 27 weeks ago. Offline
Joined: 28 Jan 2009
Posts: 1
Groups: None
Hi guys,
In P3e, is there anywhere on the screen that shows the date when we move the cursor on the barchart side, as in P3 3.1, on the top right?

Thanks.

Replies

Jim Fairchild
User offline. Last seen 10 years 37 weeks ago. Offline
Joined: 17 Mar 2003
Posts: 10
I think the original post was asking about the P3 feature called the Datometer. No this is not in P3e. However as MKSE suggests make a request to Primavera Systems.
MK TSE
User offline. Last seen 3 years 45 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
Then this one is the wish list to Primavera.
Forum Guest
User offline. Last seen 2 years 27 weeks ago. Offline
Joined: 28 Jan 2009
Posts: 1
Groups: None
Thanks Ron
What I meant was that, when you move the cursor around the graphic area, we can see the date on the top correspond to the location of the graphic area, not physically stretching the bars.

Cheers

Zubaidi
Ronald Winter
User offline. Last seen 3 years 5 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None
You have noticed a difference between P3 and P3e. P3 early activity dates are automatically changed when you change the graphical bar manually.

The same type of thing holds true for P3e (but you didn’t notice.) You think that the dates didn’t change because the dates in the activity box didn’t change. Here lies the difference.

With P3e, the graphical bar does not depict the activity early dates - it reflects the activity’s planned dates. When you change the bar manually in P3e, you change the planned dates, not the early dates. Good luck!

Ron Winter.
MATHEW JOSEPH
User offline. Last seen 12 years 28 weeks ago. Offline
Joined: 12 Jul 2004
Posts: 19
Groups: None
When you are stretching / compressing a bar graphically it shows, the dates and durations