Does P3e have "Continuous/Interruptible" CPM Setti

1 reply [Last post]
Ronald Winter
User offline. Last seen 3 years 6 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None
I have looked everywhere (including in the Help file and the manual) for the P3 equivalent of the Continuous / Interruptible Activity setting when computing the CPM. To my knowledge, P3e seems to always use the "Continuous" setting whenever computing the CPM and you have a pair of unbalanced Start-To-Start and Finish-To-Finish relationships between two activities.

P3 would give you the option of stretching the duration of the successor to meet both constraints. This is called, "Interruptible." Does anyone out there know any more about this? Without equal settings, the same schedule may show different dates on different software platforms.

Replies

Khalid Abdelaal
User offline. Last seen 6 years 4 weeks ago. Offline
Joined: 10 Jan 2001
Posts: 15
Groups: None
Dear Ronald

Schedule durations role (contigous or interruptible)is only included in P3 and doesnt included in P3e


Khalid Abdelaal