Procurement Schedule Weights

1 reply [Last post]
Manish Kanojia
User offline. Last seen 7 years 21 weeks ago. Offline
Joined: 18 Feb 2006
Posts: 3

Hi All,

I am presently working on preparation of overall EPC schedule. I want to add weights to procurement activities like:

. PO Placement

. Vendor doc. approval

. Manufacturing

. Inspection

. Ex Works

 

I can calculate weights as per total equipment cost but how to put this in primavera and then measure procuremrnt progress in order to get the S- curve for plan Vs Actual.

Please suggest how to proceed.

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

use steps and weigth the steps