Displaying Duration In Phase Title Bar

2 replies [Last post]
Brandon Jones
User offline. Last seen 10 years 8 weeks ago. Offline
Joined: 19 Sep 2012
Posts: 4
Groups: None

On my project I have all the activities organized by phase.  Is there a way to automatically display the total duration of the phase in the title?  

 

For example, if I had a phase 1A, and all the activites in phase 1A would take 30 days to complete, it would display '30' days next to where it says phase 1A.

 

Thanks in advance.

Replies

Brandon Jones
User offline. Last seen 10 years 8 weeks ago. Offline
Joined: 19 Sep 2012
Posts: 4
Groups: None

Thank you.

Kaif Mohsin
User offline. Last seen 6 years 35 weeks ago. Offline
Joined: 15 Feb 2011
Posts: 44
Groups: GPC Qatar

Dear Jones,

Yes, there is. If you are using Primavera P6 than go to the "View Menu" then to "Group and Sort" and then under the "Display Options" Tab , tick the "Show Group Totals" option and press "Ok"