Jehad Aldaoud PMP...
User offline. Last seen 4 years 22 weeks ago. Offline
Joined: 8 Oct 2010
Posts: 57
Groups: None

good afternoon to all 

 

the project manager from me to submit to him every week, week schedule show the activities we will work on it , i make filter and i used (early dates ) with the period i wanted, the problem i faced was this condition don't give me all activities that will work through that period i entered, please if there was any error in my work please advice 

 

best regards 

jihad aldoud 

 

Replies

Daniel Garcia
User offline. Last seen 12 years 50 weeks ago. Offline
Joined: 23 Dec 2010
Posts: 2
Groups: None

Hi

Try using this specifications in your filter: 

 

Level 1

Early Start    LT    (Data Date + 7 days)

Actual Start  LT    (Data Date + 7 days)

Level 2

Percent Complete    NE    100%

 

Any questions let me know

Regards

Jehad Aldaoud PMP...
User offline. Last seen 4 years 22 weeks ago. Offline
Joined: 8 Oct 2010
Posts: 57
Groups: None

Thanks for your reply harzelli, I know i must used filter but the problem is what's the right function must use to get right answer 

harzelli bouasria
User offline. Last seen 4 years 26 weeks ago. Offline
Joined: 15 Oct 2008
Posts: 42

Hi

simply use spotlight (it's easy), and when print only the requested period.

if u want to show only the activities related to this period use a filter.

Regards