Joined: 16 Oct 2010
Posts: 4
Groups: None

When I have a project with 30 buildings and the activities are pretty similar for all 30 buildings, I want the schedule to be done building wise, can I enter multiple activity / wbs codes for each activity or do I need to enter each activity 30 times?

Replies

Jehad Aldaoud PMP...
User offline. Last seen 4 years 22 weeks ago. Offline
Joined: 8 Oct 2010
Posts: 57
Groups: None

if i understand your question well, you can insert activities for one building and then make (copy=>paste) with select ( Auto-increment ) from paste options 

best regards 

jihad aldaoud