Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Reference Planning Projects with CPM details

3 replies [Last post]
Shiva Kumar
User offline. Last seen 10 years 2 weeks ago. Offline
Joined: 11 Nov 2008
Posts: 13
Groups: None
Dear GURU’s,

As a planner, i am still struggling with Critical Path Analysis (CPM Techniques) in primavera P3, so, i would request you to mail me the reference planning projects the Detailed project explanations if u have....

My mail id : shivakumaarn@yahoo.co.in / nsk1971@gmail.com

Hope u guru’s help me to clear my doubts..

Thanx in advance..

shiva

Replies

Shiva Kumar
User offline. Last seen 10 years 2 weeks ago. Offline
Joined: 11 Nov 2008
Posts: 13
Groups: None
Hi Shahul,

Thanx for your information..

shiva
Shah. HB
User offline. Last seen 15 weeks 13 hours ago. Offline
Joined: 25 Nov 2008
Posts: 773
Samer Zawaydeh
User offline. Last seen 5 years 4 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Shiva,

If you want to understand the theory, then you need to solve few examples by hand. This you can download from plenty of site on the net.

CPM is easy to understand once you have done it yourself. Try to find 10 activities example and do it yourself from start to finish and try to add the delays, extensions of time, acceleration, cost impact, etc.

With kind regards,