Add resources using Global change, P6

2 replies [Last post]
abbas india
User offline. Last seen 13 years 10 weeks ago. Offline
Joined: 12 Jul 2009
Posts: 35
Hi,

Please let me know how to add resources to activities using global change in P6.

In P3 there was add resource option.

Replies

abbas india
User offline. Last seen 13 years 10 weeks ago. Offline
Joined: 12 Jul 2009
Posts: 35
Dear Arnold,

Thank you very much for your help.

Ok after assigning the resources as you know in P3 we can export it to Excel (dbf format etc...) and we can add the budgeted units corresponding to each resourse assignment and if we import it it will be reflected in P3.

Could you please help me again how the same can be done using P6.

Many thanks,
Abbas.
Arnold Puy
User offline. Last seen 9 years 8 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147