Weighting Factor for computing % complete

2 replies [Last post]
Lalith Rathnayake
User offline. Last seen 14 years 47 weeks ago. Offline
Joined: 1 Sep 2008
Posts: 9
Dear Planners,

I am using P3 (ver.3.1)

- My program is resource loaded for Labor, Material and equipments with Cost Category values L, M, & E respectively.

- I want to use Manhours ( i.e. only labor resources) as weighting factor when computing % complete.

- When I select resource units as weighting factor (Tools --Option -- summerization -- resource units) P3 uses all resources regardless of the unit.

- How can I use only Labor resources as weighting factor for computing % complete

- Is it not advisable to load all resource categories to the schedule in this case ?

Please advice. Thank you in advance

Lalith

Replies

Lalith Rathnayake
User offline. Last seen 14 years 47 weeks ago. Offline
Joined: 1 Sep 2008
Posts: 9
Dear Thabeer,

Can you explain further ?

As I undrstood, even if you apply a filter P3 still sum up all resources (regardless of their unit) to compute budgeted quantity.

What I need is to get only the sum of manhours in the Budgeted quantity field.

Do i need to remove the other resource assignments (i.e. Material and Equipments) to achieve this ?

Please advice.

Lalith
TABEEB UR RAHMAN
User offline. Last seen 11 years 28 weeks ago. Offline
Joined: 2 Jan 2006
Posts: 8
Groups: None
define a filter, cnditional to manpower