Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Excel to P3

27 replies [Last post]
Benjamin Nicomedes
User offline. Last seen 17 years 19 weeks ago. Offline
Joined: 18 Nov 2006
Posts: 7
Groups: None
Hello Planners:

Need your help and advice regarding conveting an Excel to P3 and vice versa?

Appreciate for any help.

Thanks.

Replies

Mohamad Abdelsala
User offline. Last seen 12 years 33 weeks ago. Offline
Joined: 12 Jan 2011
Posts: 18

Hi all,

What if i am Using Excel 2007 I can Export Data from P3.1 In DBF But i Cant import it Again Form Excel because Excel 2007 Cant Save in DBF format How Can i solve this Problem?

Regards

Claus Wellendorf
User offline. Last seen 15 years 20 weeks ago. Offline
Joined: 13 Nov 2006
Posts: 4
Groups: None
Maybe a new problem:
But how do you export the "activity type" for activities I have found the hammock definition under a heading "CON" part of "Constraints" export, but where is the WBS type the Start and finish Milestone types etc
Ronald Winter
User offline. Last seen 3 years 6 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None
The Matrix Report has the ability to report on activity types. Good luck!
Arvin Dayday
User offline. Last seen 16 years 12 weeks ago. Offline
Joined: 18 May 2007
Posts: 12
Groups: None
IMPORTING DATA FROM EXCELL

A. CREATING DATA IN MSEXCELL
1.Open a New MsExcell file
2.Create your data where column headers should match the P3 compatible abbreviation (required column headings are ACT-Activity ID, TITLE-Activity Description, OD-Original duration)
3.DO NOT FORMAT THE CELLS of your excel file.
4.Saves your File in a DB4 format.
5.If prompter to save an active sheet only, click YES.
6.If prompted to save in DB4 format only, click YES.
7.CLOSE the file before importing to P3.

B. IMPORTING EXCELL DATA IN P3
1.Create a NEW P3 file
2.To Import including ACTIVITY CODES VALUE, create first the ACTIVITY CODES
3.Go to TOOLS, PROJECT UTILITIES, IMPORT
4.Click ADD, and create a new REPORT
5.Write the correct path of the DB4 file in the Enter path name and Input File cell (ex. File.dbf)
6.Click OK to close and click RUN
7.In the Output Option, point to Save in the ff. look file.
8.Click OK
9.Click CLOSE
10.Click YES, when prompted to Rerun Current Filter.


IMPORTING OR OPENING P3 DATA IN EXCELL

A. CREATING DATA IN P3
1.Create the P3 file
2.Go to TOOLS, PROJECT UTILITIES, EXPORT
3.Click ADD and create a new report file.
4.Click Content tab and insert data in the list box you want to export to EXCELL or click ALL CURRENT to export the entire data of P3 to EXCELL.
5.Click FORMAT tab, and create the DBF path and file name.
6.Click RUN and point to Save to ff: Look File.
7.Click OK to Close

B.INSERTING EXPORTED P3 TO EXCELL
1.Create a NEW file or OPEN an existing File.
2.To insert the P3 file, go to DATA, IMPORT EXTERNAL DATA
3.Click IMPORT DATA
4.Search for the exported P3 file in DBF format and click OK
5.Select a Cell, and click OK
Amreshwar Shukla
User offline. Last seen 1 year 6 weeks ago. Offline
Joined: 6 May 2003
Posts: 53
Groups: None
Hai Mr Masood Ahmed,

Give me your Email address I will send the same to you.

Regards,

A.S.Shukla
shukla@myrealbox.com


Masood Ahmed Farooqi
User offline. Last seen 7 years 24 weeks ago. Offline
Joined: 8 Jan 2006
Posts: 29
Groups: None
GOOD MORNING MY PROFESSIONAL MEMBER

CAN YOU SEND ME THIS EXEL FILES FOR EXCELL TO P3

REGARDS

M.A. FAROOQI
ruben quintal
User offline. Last seen 16 years 18 weeks ago. Offline
Joined: 26 Sep 2006
Posts: 33
Groups: None

rodel,

tnx a lot.


ben
Rodel Marasigan
User offline. Last seen 1 day 1 hour ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Ruben,

I don’t have any problem exporting/ importing data from excel in P3v3.1.
Follow this steps and it may help.

1) Open your P3
2) Select Tool-> Project Utilities-> Summarize..
3) On the pop-up Summarize Projects Enter New Project name say: ABCD on Summary Project pull down box
4) Click + on Source projects and select the project you want to summarize
5) Click the Summarize by pull down box and select activity code to the level you want to summarize
6) Set your data date and the rest items that you required and click Summarize button
7) Open the New Project created say : ABCD
8) Select Tool-> Project Utilities-> Export..
9) Select Export File – Dbase – Schedule data or any format that you’re familiar and click Modify
10) Add all the fields you wanted to export
11) Click the Format Tab and Change the Name to new Filename that you wanted (note: dbf extension max of 9 characters only) and make sure the type is [.DBF] –III/IV
12) Add sorting if required
13) Click the Selection Tab if filter or selection is required
14) Click run and select View on Screen
15) The file created with .dbf extension by default is saved to P3OUT folder.
16) Open your Excel program and on Open dialog box change the files of type to dbase files (*.dbf) and look for your exported file
17) Update your data and save it to the same format
18) Import updated database (.dbf) using P3 Tools-> Project Utilities-> Import…

Your files should be updated. Let me know it you require further assistance.

Regards,
Rodel
ruben quintal
User offline. Last seen 16 years 18 weeks ago. Offline
Joined: 26 Sep 2006
Posts: 33
Groups: None
rodel,

im trying to find a way to automate the process of making weekly reports using P3 v3.1. By using summary function, that means that i have to input the data manually into excel to make a graphical presentation/report which is very time consuming. So, using export function in P3, using same format each import and linking the datas in excel, making the report is just a matter of 2 or 3 clicks of a mouse. The problem is that summarize datas cannot be imported into excel.any idea?

Cheers,
BEN
Eugene K
User offline. Last seen 12 years 42 weeks ago. Offline
Joined: 18 Oct 2006
Posts: 47
Groups: GPC Malaysia
amir, thx for info.
moral of the story: not all upgrade may be good to us.
Amir Dadbakhsh
User offline. Last seen 3 years 23 weeks ago. Offline
Joined: 13 Oct 2004
Posts: 42
Hi guys
Be careful that Excel 2007 does not support saving in some old format such as WK1,WKS (this caused me a lot of problem ! if anyone has some excel interface which would be help to import & export data to p3, please email it for me dadbakhsh@yahoo.com)
For your information, I paste some information which I found on http://blogs.msdn.com/
The following formats cannot be opened or saved in Excel 2007:
WK1 (1-2-3)
WK4 (1-2-3)
WJ3 (1-2-3 Japanese) (.wj3)
WKS (1-2-3)
WK3,(1-2-3)
WK1,FMT(1-2-3)
WJ2 (1-2-3 Japanese) (.wj2)
WJ3, FJ3 (1-2-3 Japanese) (.wj3)
DBF 2 (dBASE II)
WQ1 (Quattro Pro/DOS)
WK3,FM3(1-2-3)
Microsoft Excel Chart (.xlc)
WK1,ALL(1-2-3)
WJ1 (1-2-3 Japanese) (.wj1)
WKS (Works Japanese) (.wks)

The following formats may be opened, but not saved to in Excel 2007:
Microsoft Excel 2.1 Worksheet
Microsoft Excel 2.1 Macro
Microsoft Excel 3.0 Worksheet
Microsoft Excel 3.0 Macro
Microsoft Excel 4.0 Worksheet
Microsoft Excel 4.0 Macro
Microsoft Excel 97- Excel 2003 & 5.0/95 Workbook
Microsoft Excel 4.0 Workbook
DBF 3 (dBASE III)
DBF 4 (dBASE IV)
Rodel Marasigan
User offline. Last seen 1 day 1 hour ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Hi Ruben,

I don’t quite understand your query. Do you mean displaying subtotal per floor level in P3v3.1 or import data from a project created into summary using Tools-> Project utilities-> Summarize?

If you only wish to display the summary total on your P3v3.1 you can use Organize and on the Total column select Bottom or Top to display your subtotal. You don’t need to import it from excel because its automatic.

If you required the percentage import from the created Project by P3 Project utilities summarize menu then use import/export facility from Tools-> Project Utilities-> Import… (I assume you are familiar import/export facilities)

Regards,
Rodel
ruben quintal
User offline. Last seen 16 years 18 weeks ago. Offline
Joined: 26 Sep 2006
Posts: 33
Groups: None
hello everybody,

i find its easy to import activity details from primavera to excel using import and P3 tools, but its kind of difficult trying to import a summarize data (eg. percent complete summarize by Floor Level).
This import can be done very easily in P3 v5.
Is there a way to do this in P3 v3.1?
tnx,
ben
John Raper
User offline. Last seen 8 years 26 weeks ago. Offline
Joined: 17 May 2004
Posts: 44
Groups: None
I implied, but didn’t state positively, that there is NO LIMIT to the number of activities if you use DBF files.
Eric EVRARD
User offline. Last seen 6 years 22 weeks ago. Offline
Joined: 4 Dec 2006
Posts: 25
Groups: None
Hello everybody,

As John Raper said, there is a limit of 2400 activities with WK1 files.
However, if you exceed 2400 acivities, you have to save 2 WK1 files with separated activities and 2 other WK1 files with the links.Once this is done save and close your WK1 files, if not no import will be possible.
First import the 1st Activity WK1 files, then import the 1st Link WK1 file on an empty primavera layout.
Do the same with the others activity & Link files on another primavera project.
Close the second Primavera Project and from the 1st you make an import of the second project by using the transfert button in the import option window.
I did it with 2950 activities and didn’t have any problems.
Regards
Ali Al-Rashed
User offline. Last seen 3 years 40 weeks ago. Offline
Joined: 11 Oct 2006
Posts: 7
hi everybody,
i have XL files can manage and control primavera file. u save alot of time and make ur work life easier .by using them.
if u need it please contact me at my-email Ali.Alrashed@hotmail.com

regards
Ali
John Raper
User offline. Last seen 8 years 26 weeks ago. Offline
Joined: 17 May 2004
Posts: 44
Groups: None
I think you have all missed one important issue here.

Open P3;
Export a layout that contains the essential fields to .WK1 or .DBF;
Open that file (it’s in the P3OUT folder) in Excel;
add the activities in the Excel file;
(this is the important bit) save the Excel file IN .WK1 OR .DBF FORMAT - DO NOT SAVE AS .XLS;
Import the .WK1 or .DBF file to P3.

WK1 and DBF formats both work well, but there is a limit of 2400 activities when using WK1.

Hope this helps
John
Hemanth Kumar
User offline. Last seen 43 weeks 2 days ago. Offline
Joined: 1 Nov 2002
Posts: 260
Groups: None
if you have access to p3 installation cd
get it
explore
find
utilities folder
open "excel" folder
there are excel interfaces

use it
to get or set to p3 activities or whatever


Ronald Winter
User offline. Last seen 3 years 6 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None
Perhaps we have been assuming too much. Here is the basics:

Open your schedule. from the menu, select ’Tools’ / ’Project Utilities’ / ’Export’. Click on the export that sounds closest to what you want and then click on the ’Modify’ button. The ’Format’ tab will list the current file name and file type. The output is sent to your C:\P3WIN\P3OUT directory unless you state otherwise. Give it a try, you can’t hurt anything. Good luck!
Prabin Kumar
User offline. Last seen 8 years 25 weeks ago. Offline
Joined: 7 Oct 2005
Posts: 11
Hi Benjamin,

You can export any data in 4 format (i.e. - .PRN, .DBF, WK1 & WKS ).
Except .PRN, all three can be open with Excel file.
and you can import any data with DBF, WK1 and WKS format only.

There is one more way to open and modify a p3 project in ms excel , i.e. by Ra->Sample->Excel folder. By this way you can fully access your project in excel , and can do some modification in your project from there.

Thanks,

Prabin Kumar
Benjamin Nicomedes
User offline. Last seen 17 years 19 weeks ago. Offline
Joined: 18 Nov 2006
Posts: 7
Groups: None
Still I could’nt get it. How could you make a wk1 files without using LOTUS 123? Could you please give an example of the format you are referring to? What is that dbf file?

Sorry guys but am really confused.Thanks.
MK TSE
User offline. Last seen 3 years 46 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
I prefer DBF format which Excel can open it also.
There is some limitation on WK1 in Excel.
Ronald Winter
User offline. Last seen 3 years 6 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None
Actually, Excel does open WK1 files. Use File / Open and then change the file template by clicking on “Files of Type” dropdown at the bottom of the screen. Then you need to use the ‘elevator’ control to the right to scroll all the way down to the bottom of the list where it says, “Lotus 123 files.” Click there and you can now see and open the file. Goo luck!
Fannie CHOW
User offline. Last seen 5 years 50 weeks ago. Offline
Joined: 17 Jan 2006
Posts: 16
hi,

I do it as below

1. Export a template, select what field you need, to databass, dbf
2. Open that dbf file and fill up the information.
3.Save the file as check the "define"
4.Import the file again.

I think the trick is the define database field of excel.

Hope it’s helpful

Cheers
Fannie
Benjamin Nicomedes
User offline. Last seen 17 years 19 weeks ago. Offline
Joined: 18 Nov 2006
Posts: 7
Groups: None
Thanks for trying to help but I can’t get it. Pls. elaborate more. Is there any other way without using Lotus 123?

Thanks again.