S Curve not fixed

No replies
steve willis
User offline. Last seen 17 years 26 weeks ago. Offline
Joined: 12 Aug 2004
Posts: 7
Groups: None
Hello all

I have been asked to run an S curve regarding Fabrication hours on site .

My problem is that this is a rolling changing curve for R & M work not a project with a fixed duration.
My hours change weekly from approved estimates either increasing or decreasing not extrawork .
I think i need to baseline on a weekly basis and run a new curve weekly or run an extra curve line showing increased work etc am i correct please help
thanks in advance

steve