Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Manhours scheduling and report analysis

2 replies [Last post]
Andrew Tan
User offline. Last seen 12 years 24 weeks ago. Offline
Joined: 9 Oct 2004
Posts: 40
Hi all,
my client wants manhours planning for construction. I have inputted in the data but what is the better way to view months vs resources with manhours loading in P3?

Thanks.
urgent.
Andrew

Replies

Shahzad Munawar
User offline. Last seen 10 years 11 weeks ago. Offline
Joined: 2 Jul 2003
Posts: 551
Groups: None
In primavera, the best way to present report to your Client is use of Graphical report by using which you can view and eloborate your resources in each month.
Dayanidhi Dhandapany
User offline. Last seen 4 years 16 weeks ago. Offline
Joined: 18 Mar 2003
Posts: 470
Groups: None
In P3, you can either use Tabular Reports or Graphical Reports to display Man-hrs requirements. Both reports will be nice for presentation.