Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Help

2 replies [Last post]
PEDRO MARTINEZ
User offline. Last seen 1 year 16 weeks ago. Offline
Joined: 10 Apr 2002
Posts: 7
I’m working with primavera P 2.0 and I need (a process) that some one helpme, how I get a graphic budget just only one activity.

I only get it a graphic budget for all project.

Replies

A.Jaffer Sadiq
User offline. Last seen 5 years 24 weeks ago. Offline
Joined: 16 Oct 2008
Posts: 33
Groups: GPC Qatar

Hi, Just give me clear Question please,

Tomas Rivera
User offline. Last seen 5 years 3 weeks ago. Offline
Joined: 2 May 2001
Posts: 139
Groups: None
I was waiting for somebody else to answer this apparently easy question.
You need a process?

If your question is what I think it is, you just need to go to the selection window and select the one activity you are interested in reporting on.

If you do not have anything in the selection window, Primavera selects all the activities of the project.