EV and PV using cost and hours

2 replies [Last post]
Abderrahim OUBDI
User offline. Last seen 3 years 45 weeks ago. Offline
Joined: 19 Jan 2020
Posts: 11

Hello,

I noticed that primavera P6, calculate EV and PV only from cost value, what if we want to calculate EV and PV from labour units.

Imagine if we have ressource loaded a schedule with hours and cost, how can we obtain the EV and PV in different point of views cost and hours separetely

Replies

Abderrahim OUBDI
User offline. Last seen 3 years 45 weeks ago. Offline
Joined: 19 Jan 2020
Posts: 11

Primavera can calculate EV and PV only for each activitiy if it is loaded in hours (labor units) but he cannot give the EV or PV in the WBS summary of the activities unless you assign the PRICE/UNIT equals to 1.

Zoltan Palffy
User offline. Last seen 3 weeks 5 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

Just go to columns and add a column it is under earned value its called Earned Value Labor Units