Maximum delay of a project in a Month

3 replies [Last post]
Arun Vasanth
User offline. Last seen 5 years 3 weeks ago. Offline
Joined: 12 Oct 2009
Posts: 200
Groups: GPC Qatar

Dear all please correct me if I am wrong...

The maximum delay of a project in a month (even the site is closed for one month also ) is 30 days only.

 

Replies

Zoltan Palffy
User offline. Last seen 3 days 5 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

already answered this on linked in also 

Raymund de Laza
User offline. Last seen 27 weeks 6 days ago. Offline
Joined: 22 Nov 2009
Posts: 762

If it falls on the month of Feb 2019 it's 28 calendar days, March 31calendar days, April 30 calendar days.

Zoltan Palffy
User offline. Last seen 3 days 5 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

NO this is a misconception.

lets say I have my steel delivery delayed for more than a month due to where the steel order ended up in the fabrication chain.

Lets say I have a critical procurment item coming from another country and the shipment does not make the boat in time and or the item is held up in customs. It could be months before there is another boat. 

also lets say it rains everyday for 30 days. how long will it take to dry out ? The delay will be 30 days + the dry out time.

Lets say it rains 40 days.