Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Sequence for Bridge

3 replies [Last post]
KRISHNENDU RANA
User offline. Last seen 5 years 12 weeks ago. Offline
Joined: 29 Jan 2019
Posts: 3
Groups: None
Sir, I want to know planning oa a bridge. Please let me know sir

Replies

Mike Testro
User offline. Last seen 5 weeks 3 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Krishnendu

The usual sequence is: Abutments > Foundations > piers > bridge span > road deck > surfacing

Best regards

Mike T.

KRISHNENDU RANA
User offline. Last seen 5 years 12 weeks ago. Offline
Joined: 29 Jan 2019
Posts: 3
Groups: None
Sir, I want to know about concrete bridge.
Mike Testro
User offline. Last seen 5 weeks 3 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Krishnendu Welcome to planning plannet.

Are you talking about a Suspemsion bridge - arch bridge - cable stay bridge - cantilever bridge - precast deck bridge - box girder bridge - steel - concrete - prestressed - or another.

Best regards

Mike Testro