project delay

3 replies [Last post]
djedilat toumi
User offline. Last seen 1 year 23 weeks ago. Offline
Joined: 14 May 2018
Posts: 9

Hello every one, 

how can i calculate the construction delay taking in account that the construction isn't finished yet?

Regards.

Replies

Zoltan Palffy
User offline. Last seen 15 hours 42 min ago. Offline
Joined: 13 Jul 2009
Posts: 2990
Groups: None

you stays will tell you that based on where you should be and where you actually are

Kathy Castle
User offline. Last seen 3 years 5 weeks ago. Offline
Joined: 17 Apr 2018
Posts: 22
Groups: None

Are you asking techniques related with construction delay analysis ? 

Zoltan Palffy
User offline. Last seen 15 hours 42 min ago. Offline
Joined: 13 Jul 2009
Posts: 2990
Groups: None

the delay is when it was originally planned to finish - when it is forecated to finish

original completion date December 15, 2018

current completion date Jnauary 15, 2019

Delay - 31 calendar days