Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Earned Value Help

1 reply [Last post]
Debosky Wale
User offline. Last seen 3 years 42 weeks ago. Offline
Joined: 18 Jul 2014
Posts: 16
Groups: None

Can someone explain to me this situation :

Is it possible to have  dropping  SPI for last 3 periods and the progress actual curve trailing on the slightly above late curve line? The forecast curve continues to show possible improvement starting from the September data period. 

PS, the programme was revised last 3 months with some efficiency introduced into the logic and construction methodology. 

 

Replies

Rafael Davila
User offline. Last seen 18 hours 58 min ago. Offline
Joined: 1 Mar 2004
Posts: 5229

Earned value method as a tool for project control

4.3. Inferences on future schedule development on the basis of SV i SPI - It is worth remembering that SV ($) and SPI (%) are considered to be measures of time deviation, but they are in fact the measure of difference between the cost of work planned and work done. In practice they are only indirectly and approximately related to the project’s time scale.

Some of us find EVM flawed for many reasons, just to name a few;

  • It does not distinguish between the works done on critical activities and activities with sufficient floats. A project could be late but EVA will not notice this problem if Earned Value exceeds Planned Value.
  • It motivates project managers to do expensive tasks first delaying cheaper activities that could have higher priorities.
  • The DOD the father of the creature warns against its use on fixed price contracts.
  • Baseline Change Management