(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Project management

14 replies [Last post]
After receiving drawings and BOQ's from client what would be the the next procedure toward project execution of Piping project.?

Replies

Raymund de Laza
User offline. Last seen 27 weeks 6 days ago. Offline
Joined: 22 Nov 2009
Posts: 762

Please open your Private Message.

Plz provide your email address, I will email all details to you.
Raymund de Laza
User offline. Last seen 27 weeks 6 days ago. Offline
Joined: 22 Nov 2009
Posts: 762

Hello Muhammad,

If you would mind, send the BOQ and Drawings and I prepare your detailed Schedule ready for Submission.

 

Regards,

Thanks if you can plz attach the erection pre commissioning and activities also.
Johannes Vandenberg
User offline. Last seen 5 weeks 4 days ago. Offline
Joined: 21 Jan 2010
Posts: 234

Hi Muhammad

Try this

Simple, Free Image and File Hosting at MediaFire

 

Regards Johannes

Thanks brother. If the piping material is provided by the client and contractror have to fabricate it and then erection what kind of wbs will be in this conditions means sample or federal wbs for piping?
Zoltan Palffy
User offline. Last seen 3 days 4 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

wbs would be how you want to break your piping down into smaller pieces like

You could have 

General and in that wbst mobilization

Submittals?Approvals list your submittals and approvals here 

Procurement list the items that you are procuring 

Then you can break you work down as per this devel of detail

Building

........Level

............Area

...............Zone

..................And any other level to here the actual piping is being installed maybe by system or large bore vs small bore

 

no xer

Thank you brother. I am new in this field. Can you plz tell me exact wbs for simple piping means mobilization, shop fab, field fab and also the activity details, this is my email Ahmad96197@gmail.com if you can send me the. .Xer file, it would be great.

Zoltan,

I suggest some changes to the order that you proposed:

1. create a wbs

2. create activities and milestones and assign activities to a wbs

3. assign relationships to activities

4. assign resources to activities

5. calculate and assign durations to activities

6. assign costs to resources and activities

7. set schedule constraints

8. calculate the schedule and the budget

9. create a baseline schedule narrative

10. issue for review

11. incorporate comments from review

12. Issue final version

Zoltan Palffy
User offline. Last seen 3 days 4 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

1. create a wbs

2. create activities and assign activities to a wbs

3. assign relationships to activities

4. assign durations to activities

5. calculate the schedule 

6. assign resources manhours and costs

7. Create a baseline schedule narrative

8. issue for review

9. incorporate comments from review

10.. Issue final version

Sorry I wanted to know about planning and scheduling of piping project. Means wbs, activities !
Zoltan Palffy
User offline. Last seen 3 days 4 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

creating a schedule to see how long the project will take to do

,
Zoltan Palffy
User offline. Last seen 3 days 4 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

pricing ?