9days delayed

5 replies [Last post]
Ahmed Sho
User offline. Last seen 4 years 44 weeks ago. Offline
Joined: 30 Apr 2018
Posts: 6
Groups: None
Hello guys It's the last day of the month and I have been assigned couple of projects to update, I have updated most of it but I have 2 projects left to update. One of this projects already have 9 days delay with a terminal float duration of 6 days. Please can anyone help me of how to update this delayed projects...Thanks

Replies

Zoltan Palffy
User offline. Last seen 3 days 21 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

do not remove the constraint at the end if it is contractual 

Ahmed Sho
User offline. Last seen 4 years 44 weeks ago. Offline
Joined: 30 Apr 2018
Posts: 6
Groups: None
Thanks alot @Mike success
Ahmed Sho
User offline. Last seen 4 years 44 weeks ago. Offline
Joined: 30 Apr 2018
Posts: 6
Groups: None
Thanks @Zoltan
Zoltan Palffy
User offline. Last seen 3 days 21 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

work faster 

Mike Testro
User offline. Last seen 1 week 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418
Hi Ahmed. Remove the end constraint flag and let the logic run free. Best regards Mike T.