Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Design Deliverables & Dependency Matrix

No replies
Paul Doran
User offline. Last seen 4 years 13 weeks ago. Offline
Joined: 19 Aug 2011
Posts: 4
Groups: None

Hi All,

I'm trying to put together a matrix that I can then mirror the logic for in P6, regarding design documentation and deliverables in the water industry, for example:

Telemetry schedule to FDS, FDS included 

EICA Spec allows enquiries to go out to the Elec and ICA Suppliers

Other docs include: Control Philosophy, P&IDs, instrument schedules etc.

If anyone already has a matrix / flowchart, or can point me in the direction of any info it would be appreciated.