MS Project - Thirds of Months?

2 replies [Last post]
Andrew McLean-Reid
User offline. Last seen 3 years 33 weeks ago. Offline
Joined: 22 Jan 2013
Posts: 4
Groups: None

One of my Project Managers just asked me a question I couldn't answer.

:-o

You can imagine my acute embarassment and changrin. The very thought of being less knowledgable than a PM makes me shudder, so any help would be much appreciated.

Why does MS Project have the option of displaying thirds of months on the timeline? You can display Beginning/Middle/End (BME) of a calendar month.

Who reports in this manner? Why would you need to see this?

Has anybody heard of this before?

 

AMR

Replies

Anthony Lowery
User offline. Last seen 12 weeks 1 day ago. Offline
Joined: 24 Jan 2014
Posts: 21

In the final selection for the schedule printout, MSP will select the timescale for best fit on the full page.  The scale selected for viewing really depends on the size screen you have to view it when you select "view entire project".