Manpower loading

2 replies [Last post]
vigeeth salian
User offline. Last seen 6 years 18 weeks ago. Offline
Joined: 25 Feb 2016
Posts: 10
Groups: None

hi,

guys i have 30activities, which is finish to start.

and i have only 2men to complete all 33 activities.

how can i allocate just 2men.

My total manpower after allocation should show me 2men.

 

Thanks & Regards,

 

Vigeeth

Replies

Assign those who will do the work, enter resource availability (two men) and then level project resources.

The software will organize the sequence of work so that at any time not more than two men will be used. It does not matter if your activity dependencies are FS or others, or no dependencies at all.

Mike Testro
User offline. Last seen 1 week 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Vigeeth

Just allocate 2 men to each of the tasks - when the logic is FS with no lead lags the histogram should show a straight line of 2 men allocated.

Best regards

Mike Testro