Hello everyone,
I have a question regarding planned costs for future periods.
Example (please correct my procedure if i do something wrong):
At start:
Activity with original duration of 2 months costs 1000.
Planned cost by default is Month 1 - 500, Month 2 - 500. Baseline saved.
After month 1.
Actual cost is 200 only, also Contractor asks for extention, so I extend duration at completion to 3 months. Original remains as 2 months.
I Update progress for past month, then I Save actual performance of 200 in financial period 1. Baseline saved.
After month 2.
Actual cost is 200, but Contractor promises to finish it on time (end of Month 3).
I Update progress for past month, then I Save actual performance of 200 in financial period 1. However, after updating progress Activity status automatically changes to Completed in Month 2 (as it was initially planned). But I don't want it, besides I want to see planned cost for Month 3, which is now shown as 0.
I think that both issues related to original duration. So I cancel completion status, and extend original duration so it is equal to Duration at completion (not sure of this).
Planned costs now changed: Month 1 - 333, Month 2 - 333, Month 3 - 333.
But we know that Cumulative Actual cost for Month 1 and 2 is 400, and at this point by logic in Month 3 Planned cost must be remaining cost =Planned-Actual=1000-400=600. But it is seen from Planned costs that Month 3 is just 333.
So, what do I do wrong?
1. Can I change original duration? Do I have to do this when I use Update Progress?
2. How to see correct remaining Planned cost for future period?
3. What technique should I use in this case - Update Progress or something else?
Thanks in advance!