Weather

2 replies [Last post]
ronron martinez
User offline. Last seen 7 years 11 weeks ago. Offline
Joined: 19 Nov 2009
Posts: 41

Dear All,

For the Activity schedule and the resource loading is it required to included the hours or percentage for the weather factor.

Regards

Replies

Zoltan Palffy
User offline. Last seen 2 days 21 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

that depends on the specifications but regardless I would certainly include both.

I would create an anticipated adverse weather in my calendar and assign my exterior work activities to this calendar.

I would also add resource to my schedule so that you can track the required budgeted manpower as well as the actual manpower on the project. 

Rafael Davila
User offline. Last seen 12 hours 50 min ago. Offline
Joined: 1 Mar 2004
Posts: 5228