Problem to make Recovery Plan as a new Baseline

2 replies [Last post]
Muhammad Tahir
User offline. Last seen 8 years 27 weeks ago. Offline
Joined: 4 Jul 2012
Posts: 7
Groups: None

Hi Guys,

I prepare a recovery plan from last updated program, i was monitoring the progress based on total Budgeted Cost and all activities were Phisical % type. My project was in delay due to our mistake so i adjust the remaining duration by increasing the productivity and changing some logic. Now i want to use this as a new baseline so which values i have to use. Remaining total Cost or Budgeted total Cost as Planned Value?

Replies

Robin Clare-Talbot
User offline. Last seen 2 years 51 weeks ago. Offline
Joined: 17 Aug 2010
Posts: 28

I would recommend using as planned value, as if you are mitigating by using additional resources, which I assume is how you have adjusted your productivity, or longer working hours per period etc, your at complete cost will go up, so you need to compensate somehow.

50% of $100 is $50 so 50%, but 50% of your now $120 is not $50 anymore, if that makes sense.

nadeem Ghulam Qadir
User offline. Last seen 8 years 26 weeks ago. Offline
Joined: 11 Oct 2015
Posts: 4
Groups: None

Dear Sir...

Kindly tell me how to calcaulte the planned %  and actual %  and time elapsed of project. with example...

I am waitng  your positive response ..

With Regards

Nadeem