New specs restrict the use of SS & FF lags

No replies
Steve Eiden
User offline. Last seen 7 years 9 weeks ago. Offline
Joined: 16 Sep 2004
Posts: 19
Groups: None

To all:

Have increasingly run into the restriction of using no SS or FF lags and of having to remove redundant logic. In ACOE specs and now on a non-military project in Hawaii. Do not think they have the legal right to request this as these items are all part of generally accepted scheduling practices. Does anyone know if this kind of restriction has any academic source or standard to back up its use in a scheduling specification