14 day rolling calendar

2 replies [Last post]
Ian McDonald
User offline. Last seen 8 years 36 weeks ago. Offline
Joined: 6 Aug 2015
Posts: 2
Groups: None

Hi

Does anyone know how to set a 14 day rolling calendar in P6.

Im trying to make it 11 days working 3 days non working.

Replies

Rafael Davila
User offline. Last seen 4 hours 35 min ago. Offline
Joined: 1 Mar 2004
Posts: 5229

There should be a way to model recurring period, rolling calendars are not uncommon.

RollingCalendar photo RollingCalendar_zpsvwh88rol.jpg

Zoltan Palffy
User offline. Last seen 3 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

you will have to do this manually since it changes every 2 weeks