Revised Planned Percentage

5 replies [Last post]
Jithin Kambhikanam
User offline. Last seen 3 weeks 1 day ago. Offline

Hello Gents/Ladies,

 

When you are on Contractor side when can you allowed to change the planned %. As on a Contractor side you would issue a planning package which comes with a S curve which says that that at this week you would complete this much % of progress (Planning package - Schedule , S Curve , Weightage, narrative etc) for which you need clients approval which would be then used as a reporting basis weekly  / monthly.

Can you change the Planned % as you like (contractor) or to change the planned % you need clients approval which you would only get if a deviation in the inital scope is proven.

 

Thanks

Jithin

Replies

Raymund de Laza
User offline. Last seen 31 weeks 5 days ago. Offline
Joined: 23 Nov 2009
Posts: 762

You are Welcome Jithin...

Jithin Kambhikanam
User offline. Last seen 3 weeks 1 day ago. Offline

Thanks Ray,

Thats the answer i was looking for and the same thing is what i followed from the start. I just needed a confirmation of what i did was correct. Thank you very much.  

Raymund de Laza
User offline. Last seen 31 weeks 5 days ago. Offline
Joined: 23 Nov 2009
Posts: 762

Hi,

You can only change when there is instruction from the Client to submit a Revised Baseline Schedule due to Changes & Modifications.

Regards,

Jithin Kambhikanam
User offline. Last seen 3 weeks 1 day ago. Offline

Thanks Ray,

But can you change the Planned % without clients approval from the first planned % which was submitted (S curve) and approved by client. Are we (Contractor) authorised to change the planned % without clients approval.

 

ItemBaseline Planned %Actual Completed %
Engineering  
Procurement  
Construction  

Thanks

JK

Raymund de Laza
User offline. Last seen 31 weeks 5 days ago. Offline
Joined: 23 Nov 2009
Posts: 762

HI,

The Contractor is solely in Control of the Program such as the Activities sequencing, Costs, durations, etc, therefore the Planned % shall be according to Contractors ability to execute the Schedule.

 

Regards,