Load Labor Units/ Manpower in an Updated Schedule

3 replies [Last post]
deepak khundrakpam
User offline. Last seen 8 years 38 weeks ago. Offline
Joined: 23 Oct 2010
Posts: 3
Groups: None

Dear Friends,

My Client is asking to load resources ( Manpower ) in the existing Primavera Schedule (P6)  which is already updated . I have never came across such situaion  and am not sure , technically can it happen. Can ayone shed some light on this.

Thanks,

Deepak

Replies

Zoltan Palffy
User offline. Last seen 3 days 20 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

my answer reains that same 

add a resource to each activity and put in the budgeted units (manhours for each activity)

then just update your remaining manhours for activities that are in progress 

for your activiites that are completed update the reamining units as zero

deepak khundrakpam
User offline. Last seen 8 years 38 weeks ago. Offline
Joined: 23 Oct 2010
Posts: 3
Groups: None

Thanks for your valuable response!! But do we need to load the Manpower in all the activities including the completed ones. and what about the ongoing activities ?? we shall put only the remaining units or total units is also required to show a realistic Manpower Histogram !!

Thanks in advance!!

Zoltan Palffy
User offline. Last seen 3 days 20 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

yes you can do it add a resource in the resource dictionary 

then add a resource to each activity and put in the budgeted units (manhours for each activity)

then just update your remaining manhours for activities that are in progress