P6 RESOURCE PROFILE

3 replies [Last post]
Cecil Soliva
User offline. Last seen 6 years 29 weeks ago. Offline
Joined: 17 Apr 2004
Posts: 20

Dear Planners,

I would like to brought this to the group to get information how my resource graph shows like a step of a stair as per attachment. May someone could make me understand/explain how to make this profile smooth. The Time scale is in weekly progress Plan. But if it is in monthly (timescale) it shows good.

 

Thank you,

 

Cecil

2363
p6_resource_profile.jpg

Replies

Raymund de Laza
User offline. Last seen 28 weeks 48 min ago. Offline
Joined: 22 Nov 2009
Posts: 762

You are welcome...

Cecil Soliva
User offline. Last seen 6 years 29 weeks ago. Offline
Joined: 17 Apr 2004
Posts: 20

Thanks raymond..I got it.

Raymund de Laza
User offline. Last seen 28 weeks 48 min ago. Offline
Joined: 22 Nov 2009
Posts: 762

Cecil,

In User Preferences.. Resource Analysis.. Set the interval to days...

 

 