Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Hi Everyone

2 replies [Last post]
Ken Nems
User offline. Last seen 9 years 22 weeks ago. Offline
Joined: 5 Mar 2014
Posts: 7
Groups: None

Hi Everyone,

I am new planner who's being asigned to build a draft programme for Earthworks. Please can any one help me out with a basic activities that is required for an earthworks programme in rail or kindly advice me on how to go about it.

Many thanks.

Ken.

Replies

Ken Nems
User offline. Last seen 9 years 22 weeks ago. Offline
Joined: 5 Mar 2014
Posts: 7
Groups: None

Hi Mike,

Many thanks for this information, I think I might just ask the PM for the contract documents that might give me a head way on what is required.

 

Ones again many thanks for the help.

Regards,

Ken

Mike Testro
User offline. Last seen 5 weeks 3 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Ken

It is not simple.

An earthworks programme for a linear project such as a rail track starts with the engineer's schedule of Cut to Fill.

This is a matrix in the contract documents that sets down:

1. Location and volumes of excavation zones.

2. Classification of the soil - there are usually 5 types - three of which will be acceptable for fill material.

3. These are Granular - Cohesive - Chalk each of which needs different handling techniques.

4. Location and volume of the fill zones.

From this information you can calculate the number of haul units which is the key factor in the duration of the project and the duration of each cut to fill operation.

The best software to use is a time / distance format such as Tilos or Asta PowerProject in task per line mode.

Having established all that you need a task for:

1. Each cut to fill zone

2. Drainage

3. Track bed

Best regards