Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Setting up Baseline Schedule

3 replies [Last post]
Albert Balogo
User offline. Last seen 9 years 26 weeks ago. Offline
Joined: 9 Jun 2008
Posts: 44

Hi Planners,

 

Would you please help me. I was trying to stablish a baseline schedule with the current update (current is not updated yet),  but baseline finish daes goes beyond the current dates. The question is HOW TO RESET THE BASELINE SCHEDULE? so that the current and baseline finish dates will be the same.

 

Thanks in advance

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 5 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

oracle p6 forum 

Sarah Aseoluwa
User offline. Last seen 9 years 6 weeks ago. Offline
Joined: 5 Mar 2015
Posts: 4
Groups: None

Where?

Zoltan Palffy
User offline. Last seen 3 weeks 5 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

I already answered this in the other forum