Make UTID's Useful

No replies
Mike Testro
User offline. Last seen 4 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi All

It is an easy task to make Unique Task Indicator's more useful that a set of random computer generated numbers.

For instance if you hav a task for plastering on the 6th floor of the west wing on block A the UTID would be:

AW06Plas

Now you can use this to filter on any task in the project plus multiple other useful applications.

Try it and make life easy for yourself.

Best regards

Mike Testro