Hi,
I am relatively new to planning. I am planning my first job, to build 4 large pipelines. The pipelines are over 500m in length each, and run parallel to each other. Each pipeline needs to grow at the same time i.e. not construct the first pipe, then the second etc.
I have input each activity to build each pipeline, and input the logic for each pipeline i.e. install the first section of pipe before the second section etc.
I have done it on the basis of having infinite resources. However, this will not be the case. There may only be one crane for example.
My question is, although I have put the actual logic in, how do I influence the schedule in order so it is built in a particular way? E.g. Pipeline 1 section 1 > Pipeline 2 section 1 > Pipeline 3 section 1 > Pipeline 4 section 1 > Pipeline 1 section 2
Do I just use logic link, even though it's not the actual logic.
Any advice would be much appreciated.
Replies