Engineering / document approvals in Primavera P6

6 replies [Last post]
Haroon Rasheed
User offline. Last seen 9 years 4 weeks ago. Offline
Joined: 14 Oct 2008
Posts: 19
Groups: None

Hello,

I am creating a new schedule and want to understand best practices by experts here.

How are you managing engineering or document approvals in your schedule?

  1. Submission/Approval - as a single activity?
  2. Submission linked to approvals - as separate activities?
  3. Or you manage it in a separate software and update percentages only to WBS summaries?

Thanks in advance,

Haroon

Replies

Kannan CP
User offline. Last seen 3 weeks 3 days ago. Offline
Joined: 12 Jun 2008
Posts: 290
Groups: None

Hi Mike,

I agree with you that the submission/approval should be done for each WP.

Best Regards

Kannan

Haroon Rasheed
User offline. Last seen 9 years 4 weeks ago. Offline
Joined: 14 Oct 2008
Posts: 19
Groups: None

Thank you for the clarity - @kannan & @Mike.

-Haroon

Haroon Rasheed
User offline. Last seen 9 years 4 weeks ago. Offline
Joined: 14 Oct 2008
Posts: 19
Groups: None

Thank you for the clarity - @kannan & @Mike.

-Haroon

Haroon Rasheed
User offline. Last seen 9 years 4 weeks ago. Offline
Joined: 14 Oct 2008
Posts: 19
Groups: None

Thank you for the clarity - @kannan & @Mike.

-Haroon

Mike Testro
User offline. Last seen 4 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Kannan

You are absolutely correct but there are some further refinements that I would suggest.

The design and approvement cascade should be set up for each work package and linked to start of the package work.

The cascade should be as you suggest Design Approval + Order + Work Design + Procurement + Delivery + Port Clearance + Stock on Site.

This simple cascade should be set ALAP when linked to the work package Start Work Milestone.

Best regards

Mike Testro

Kannan CP
User offline. Last seen 3 weeks 3 days ago. Offline
Joined: 12 Jun 2008
Posts: 290
Groups: None

Haroon,

 

Always divide the engineering document submission in to 3 section

 

1. Submission duration

2. Review/Approval duration as per the contract(may be approved or to resubmit or approved as noted)

3.Follow up and final approval (consider 2-3 revision durations)

 

Procument may start after no.2 (may be it is approved as noted) but the manufacturing you cant finish without the final approval.

For construction related design, you should get the final approval no.3 prior to any works (otherwise you can start in your own risk)

Regards

Kannan