Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Submission Activities

No replies
ceyhun altundag
User offline. Last seen 9 years 44 weeks ago. Offline
Joined: 9 Sep 2013
Posts: 4
Groups: None

Hello, 

I'm working in a project that has contractual certain dates for submissions of documents. How should I link these activities? Especially, if I figure that I can send these documents earlier than the contract date according to program but I dont want client to see these dates  earlier in the program.

Also there is one more issue, some documents are predessors for others and contratual submission dates for these activities are same.

For Example, 

Act A is predessor for Activity B and contractual submission dates are same.

My Activity A is ''Preparing and submission of Vavle List''  I put this activity's early finish to 1.sep.14 with using certain lag (which I dont want to use). 

Activity B is ''Preparing and submission of Spare Parts'' (Act A is predessor for this activity) and it has the same contractual submission date 1.sep.14 .

How can I show this?

Thanks in advance.

Rgds,

Ceyhun Altundag.