Hello,
I'm working in a project that has contractual certain dates for submissions of documents. How should I link these activities? Especially, if I figure that I can send these documents earlier than the contract date according to program but I dont want client to see these dates earlier in the program.
Also there is one more issue, some documents are predessors for others and contratual submission dates for these activities are same.
For Example,
Act A is predessor for Activity B and contractual submission dates are same.
My Activity A is ''Preparing and submission of Vavle List'' I put this activity's early finish to 1.sep.14 with using certain lag (which I dont want to use).
Activity B is ''Preparing and submission of Spare Parts'' (Act A is predessor for this activity) and it has the same contractual submission date 1.sep.14 .
How can I show this?
Thanks in advance.
Rgds,
Ceyhun Altundag.