Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

start date is not critical

6 replies [Last post]
moutaz aldeib
User offline. Last seen 2 years 27 weeks ago. Offline
Joined: 31 Dec 2003
Posts: 291
Groups: None

Dear Planners,

I am establishing a schedule on MS Project 2010, after finishing the schedule I detected that the start date of the project is not critical, it has 35 days float. Eventhough no constraints applied and no open ends exist.

Regards,

Moutaz

Replies

Rangarajan Ramaswamy
User offline. Last seen 1 year 30 weeks ago. Offline
Joined: 1 Dec 2009
Posts: 24

Please check the following :-

1. The Project finish date is matching with the schedule finish date

2. If still the start date is showing float it means that somewhere the relation is open or a constrain in the project is driving the CRITICAL activities.

3. You can send the file to me to check for issues.

 

Patrick Weaver
User offline. Last seen 3 days 6 hours ago. Offline
Joined: 18 Jan 2001
Posts: 373
Groups: None

Possible options (assuming there is a difference between the milestone and the first activities float)

  1. The project start date is defined as a constraint on the first activity not the milestone and the milestone is scheduling from the project calendar start
  2. Different calendars allocated
  3. The first activity is scheduled ‘As late as possible’
moutaz aldeib
User offline. Last seen 2 years 27 weeks ago. Offline
Joined: 31 Dec 2003
Posts: 291
Groups: None

Dear Gary,

Sorry that is what I mean, the first task is successor to the milestone date.

Best,

Moutaz

Gary Whitehead
User offline. Last seen 4 years 46 weeks ago. Offline

the first task should be the sucessor of the start milestone, not predecessor

moutaz aldeib
User offline. Last seen 2 years 27 weeks ago. Offline
Joined: 31 Dec 2003
Posts: 291
Groups: None

Yes, Gary it is a milestone and the first task is the predecessor of this milestone.

Regards,

Moutaz

Gary Whitehead
User offline. Last seen 4 years 46 weeks ago. Offline

when you say start date is not critical, do you mean start milestone?

 

If so, check the first task that is on your critical path has a predeccesor of the start milestone