Differences between using FS or SS Relations With Milestones Activities ??

3 replies [Last post]
Yaser A. Al-Bustanji
User offline. Last seen 1 year 7 weeks ago. Offline
Joined: 12 May 2010
Posts: 27
Groups: None

Dear Freinds;

Are there any differences between using FS or SS relations with Milestones activities ?

 Please Advise

Replies

Mike Testro
User offline. Last seen 1 week 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Yaser

Linking from a milestone the same calendar rules apply - otherwise the is no difference.

Best regards

Mike Testro

Yaser A. Al-Bustanji
User offline. Last seen 1 year 7 weeks ago. Offline
Joined: 12 May 2010
Posts: 27
Groups: None

Thanks but my question about the effect of this relations when the predecessors is milestone (Zero Duration) in p3 or 

Mike Testro
User offline. Last seen 1 week 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Yaser

A SS Link will start at the start of the predecessor task and a FS will link come from the end of the predecessor.

In Asta PowerProject a FS/SS link will take on the calendar of the predecessor but a FF link will use the successor calendar.

Best regards

Mike Testro