How to track,monitor road project without entering resources in MSP Program?

4 replies [Last post]
vipin thormothe
User offline. Last seen 11 years 11 weeks ago. Offline
Joined: 4 Dec 2012
Posts: 5
Groups: None

As we are from client side, EPC has submitted a MSP program without resources allocation. Is it possible to monitor and track the progress in his given schedule?

Replies

Evgeny Z.
User offline. Last seen 39 weeks 4 days ago. Offline
Joined: 13 Jan 2008
Posts: 442
Groups: None
vipin thormothe
User offline. Last seen 11 years 11 weeks ago. Offline
Joined: 4 Dec 2012
Posts: 5
Groups: None

Hi Mike,

Thanks a lot for your valuable inputs. I have tried importing the MSP program in Primavera 8.1 and successfully imported. But now for tracking the progress i am using physical % complete data. In a road project of 244 kms, in India, resources are the big issue so EPC contractor is not able give the resource inuts. Weekly updation of the physical % comlpete work gives the basic information about the progress but budget and financial data,s curve is not available.

 

 

Regards,

Vipin

vipin thormothe
User offline. Last seen 11 years 11 weeks ago. Offline
Joined: 4 Dec 2012
Posts: 5
Groups: None

Hi Mike,

Thanks a lot for your valuable inputs. I have tried importing the MSP program in Primavera 8.1 and successfully imported. But now for tracking the progress i am using physical % complete data. In a road project of 244 kms, in India, resources are the big issue so EPC contractor is not able give the resource inuts. Weekly updation of the physical % comlpete work gives the basic information about the progress but budget and financial data,s curve is not available.

 

 

Regards,

Vipin

Mike Testro
User offline. Last seen 5 weeks 3 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Vipin

Has the contractor followed the programming requirements in the specification?

If it allows a non resourced MSP programme then there is not much you can do about it unless there is an an approval procedure to be followed when you can try and get it resourced.

You can monitor progress on an MSP with or without resources but in my opinion it is too lightweight for a road project

Linear construction requires a time/chainage chart such as Tilos or Vicos - even Asta PowerProject v 12 would be better.

Best regards

Mike Testro