Linear Scheduling

1 reply [Last post]
Michael Morrison
User offline. Last seen 5 years 12 weeks ago. Offline
Joined: 10 Jan 2012
Posts: 2
Groups: None

Hi All,

Does anyone have a copy of an Excel sheet that can perform Linear Scheduling for road works (pipe line, drainage and resurfacing) of a busy street?

If you do kindly email it to use private messaging Cheers,

Michael

Replies

Mike Testro
User offline. Last seen 4 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Michael - Welcome to Planning Planet

It is very easy to set one up using X - Y graphics.

Pretty to look at but no criticality.

Better to invest in proper software such as tilos or Asta Power project that has a Time Chain display facility.

Best regards

Mike Testro