Pre-Construction Activities

4 replies [Last post]
Moustafa Moustafa
User offline. Last seen 44 weeks 4 days ago. Offline
Joined: 8 Jul 2012
Points: 2
Groups: None

Hi All, 

I am trying to complete a schedule that another planner has already started. Unfortunately, he hasn't linked his pre-construction activities together. For example, there are preparation for submittal activites with predecessor "effecvtive start date"; they all start at the same time. 

My Question is, How can I link those activies in a way that I do not have them all start at the same time and not delay my construction activites. Should I look at the free float? please explain as I am new to planning. 

Thanks 

Replies

Nicky,

I disagree.

It seems highly unlikely that you would have the available manpower to start all your general submissions on day 1.

And using SF links (presumably with negative lag?) for technical submissions is a bad idea -it means delayed submissions will never delay site works -which is of course not true.

Nicky N
User offline. Last seen 40 weeks 4 days ago. Offline
Joined: 6 Feb 2012
Points: 5
Groups: None

some technical submittals should be completed before starting the work on site and some submittal can go in hand with the construction work for ex.mobilization submittals. For general submittals, it all can be started in same date as soon as you complete the mobilization of manpower to site. But for technical submittal try to use SF relationship and find the best period to fit in.

Depending on the project scope, some of the pre-construction activities will have a logical sequence in themselves that you should enter.

For example, you wouldn't design an MCC until you have designed the motors it will be controlling.

 

Once you have done this, you can then schedule the remainder based on total or free float, as the previous answer suggests.

 

Most software has the capability to do "resource levelling", which will automatically adjust the activity dates to fit with available resources, based on user-defined priorities (eg total float). Some software is good at this, some not so good. And it only works if you have a resource loaded programme.

 

If you can't or don't want to use resource levelling, you can either use logical links to spread the activities out, or early start constraints. There are pros & cons to both approaches.

if you plan to make an adjustment without affecting your predecessor activities, you can made ammendment based on available Free Float. if you have no constraint other than meeting your project completion date, you can use Total Float as a refference.

Market Place

EVA18 is the major UK event for Project Control knowledge, know-how and networking. EVA is a conference organised by a project management practitioner for project practitioners and stakeholders
A comprehensive product suite with the flexibility to meet the varying needs of everyone involved in running projects
The book is designed for users of earlier versions to upgrade their skills and for new planners to learn the software.
We want to build software that solves real problems, allow people to work more productive and happier.
A user guide and training manual written for professionals who wish to learn how to plan and control projects in an established Primavera Enterprise environment with or without Resources & Roles.