Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

effect of mile stone on scheduling

3 replies [Last post]
Sunil Babu
User offline. Last seen 4 years 37 weeks ago. Offline
Joined: 8 Nov 2010
Posts: 156

Hi Friends,

If we put some milestones for some activity start in WBS levels...will it affect

any problem while scheduling..will it make any effect in activity floats..?

your views are most welcome.

Regards

Sunil.

Replies

Rafael Davila
User offline. Last seen 11 hours 42 min ago. Offline
Joined: 1 Mar 2004
Posts: 5229

Milestones are activities and as such they might have an impact on the successors. They are not always dummy links only good to highlight some events, they can even be driven by their own calendar, can be assigned costs and even resources. Yes even resources and this might have an impact on resource leveling even when the demand of the resource is for 0 time, here might be very dependent on your specific software.

It is common to use contractual milestones and set a finish constraint to the milestone to show up criticality on intermediate contractual milestones. They can affect how float is displayed up to the point to create negative float and make late dates earlier than early dates if your software uses pseudo mathematical algorithms that break the rules of physics (wrong modeling).

Please note that I am not telling that the use of constraint to show criticality is wrong, but that the implementation by some software can be wrong.

In the following figure you might see how different milestone settings will have. Take particular attention to Milestone at phase 4 that has an unattained finish NLT (no-latter-than) constraint, the software displays it critical ( 0 float) but did not fooled the laws of physics by making late earlier than late dates, therefore it did not created negative float and will never yield S curves where Late Curve at a portion or at the whole will be on top of the early curve an incomprehensible pseudo mathematical result. 

Photobucket

Best regards,

Rafael

Sunil Babu
User offline. Last seen 4 years 37 weeks ago. Offline
Joined: 8 Nov 2010
Posts: 156

Hi Daniel,

Thank u...

Daniel Limson
User offline. Last seen 4 years 39 weeks ago. Offline
Joined: 13 Oct 2001
Posts: 318
Groups: None

Sunil,

I dont think you can put, add  or create a Milestone in the WBS level. You can only add a milestone at the activity level.

A milestone (start or finish) has a zero duration so there is no effect to subsequent activities in terms of float. It is actually a good idea to add a start milestone to a group of activities especially relating to access dates or interface dates.

Cheers,

Daniel