Resource Levelling

1 reply [Last post]
Hlamalani Baloyi
User offline. Last seen 11 years 41 weeks ago. Offline
Joined: 20 Jan 2012
Posts: 18
Groups: None

My schedule is about 9000 lines with about 500 resources, Is there a way of auto-levelling the resources and not affect the finish date of the project?

Replies

If resources are sufficient the finish will not move.

The purpose of resource leveling is creating realistic plan. Applying resource leveling you may find what resources are needed to be able to finish on specified date.