Assigning a Material Resource in P6

1 reply [Last post]
SM PUM
User offline. Last seen 10 years 8 weeks ago. Offline
Joined: 15 Nov 2011
Posts: 77
Groups: None

Hello All Planners.

Please have a look at following example;

I added a Material Resource Named "Crushed Aggregates" in my schedule.I have changed resource type to "Material" and adjusted the price per unit.No the unit of measure that i want to keep is "Cu.m".The issues that i am facing are,

1- I am not able to find an option to make my resourse loading a "spread loading" i.e, I want to tell primavera tha 1000 C.m of crush is required for a certain activity in 2 weeks.The only way i find is assigning price per unit and then if i assign this esource to the activity,then it multiplies the price per unit with the duration,that i do not want.

I want to give my resuorse a certain price and qty that should be spread on total duration of activity.

 

I hope my question is clear.Like in primavera Risk analysis there is option of "spread loading " and "point loading".

If not then how you assign material resource to your activities.please guide.

 

Thanks

Replies

Raymund de Laza
User offline. Last seen 30 weeks 4 days ago. Offline
Joined: 23 Nov 2009
Posts: 762

Hi,

Manually edit the Budget Units on the assigned resource.