Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Constraints in P6

No replies
Dave Scott
User offline. Last seen 12 years 10 weeks ago. Offline
Joined: 13 Dec 2011
Posts: 4
Groups: None

I'm semi-new to P6.

I'm trying to hold a date in my schedule.  In the bottom activity box I have the dates selected that I want to hold, but in the schedule the * does not appear.  When I update the schedule, it changes all 100% completed dates to the data date.  If I change the data date, it changes all 100% done activities to that data date.

Any input would be apreciated.

Dave