Am I right in my thinking with the following.....
I have assessed a PMI and impacted the last Accpeted programme, as a result there is a 2 day impact to Planned Completion.
However when I then put these works in the current Draft Programme (with submission imminent), the is no delay impact as there is 2 days float and therefore the works slot in and and become Critical.
My view is that we are still entitled to the 2 day delay costs and therefore the Contract Completion should move out to accommodate the 2 days (albeit with the planned Completion remaining in the same place and therefore the CTTR bar extends by 2 days).
Because the impact must be assessed against the accpeted programme at the time the impact was raised (even if you know the logic has subsequently changed within the draft programme you are currently working on).
Any thoughts??
Replies