Establishing a Critical Path

2 replies [Last post]
AB Timo
User offline. Last seen 9 years 4 weeks ago. Offline
Joined: 22 Jun 2011
Posts: 108
Groups: None

Hi,

People working in primavera must know that when you schedule your programe of work after adding relationships,it makes its own critical path based on the longest path having 0 float...

Now I have a schedule with a critical path and i want to change my critical path.I know you can change it if you know how to play with the activity relationships ,but is there any other method that is time saving and shorter then the above mentioned one?????????????????????

Regards

Engr.Faiz

Replies

AB Timo
User offline. Last seen 9 years 4 weeks ago. Offline
Joined: 22 Jun 2011
Posts: 108
Groups: None

I got it...thank you

Gary Whitehead
User offline. Last seen 4 years 45 weeks ago. Offline

There are 4 ways to change you critical path:

1) Ammend the rules defining what is critical (schedule, options)

2) Change the relationships

3) Change the durations

4) Change the constraints

 

You shouldn't be looking for the quickest method, but the one which gives you the most realistic schedule.