ji wei
User offline. Last seen 12 years 43 weeks ago. Offline
Joined: 14 May 2010
Posts: 9
Groups: None

we have established the weekly report by excel database, and form the plan and forcast curve.

I want to ask the difference between the plan and forcast curve?

When should I input the forcast data?

Thanks

Replies

Khaja Sharief
User offline. Last seen 10 years 9 weeks ago. Offline
Joined: 9 Sep 2008
Posts: 44

Plan Curves represent the baseline plan

Forecast curve will project the plan of remaining work in light of till date progress and future outlook.

i.e. forecast curve = actual curve + plan for the remaining work

Gary Whitehead
User offline. Last seen 4 years 46 weeks ago. Offline

actual and forecast are both parts of the same curve -actual part of it for the past, forecast for the future.

ji wei
User offline. Last seen 12 years 43 weeks ago. Offline
Joined: 14 May 2010
Posts: 9
Groups: None

Thanks for your reply!

but if I update each week with new data, so what's the difference between actual curve. By the way, all our curve was formed by completed work quantities.

 

487
curve.jpg

Gary Whitehead
User offline. Last seen 4 years 46 weeks ago. Offline

plan curve uses your baseline dates, and hence does not change (unless you rebaseline)

forecast curve uses your latest update dates. Input the forecast data each week as the schedule is updated.